Actual Labor Units Is Not Getting Updated In P6 EPPM After Updating The Progress In Team Member
(Doc ID 3042350.1)
Last updated on SEPTEMBER 06, 2024
Applies to:
Primavera P6 Team Member - Version 21.12.11.0 and laterPrimavera P6 Enterprise Project Portfolio Management Cloud Service - Version 21.12.11.0 and later
Information in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
---------------
Actual Labor Units is not getting updated in P6 EPPM after updating the progress in Team Member
EXPECTED BEHAVIOR
-----------------------
Actual Labor Units is getting updated in P6 EPPM after updating the progress in Team Member
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
- Log into P6 Web.
- Go to Projects-->Activities, choose one Activity, then go to Team Member, mark Activity as started then mark it as completed and Save.
- Check the Actual Labor Units in P6 EPPM (without even moving the DD out and Scheduling), the Actual Labor Units is getting updated.
- Go to Projects-->Activities, choose another Activity, then go to Team Member, mark Activity as started and save. Then check in P6 EPPM on the Activity status values, it is shown as In Progress.
- Then mark the Activity as completed in Team Member and save. Check the Actual Labor Units in P6 EPPM, the Actual Labor Units is not getting updated.
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |