Project Preferences of an EPS Node are Reset to Default Values and Not Applied Upon Addition of New Projects
(Doc ID 3058887.1)
Last updated on FEBRUARY 04, 2025
Applies to:
Primavera P6 Enterprise Project Portfolio Management - Version 15.1.0.0 to 23.12 [Release 15.1 to 23.12]Information in this document applies to any platform.
Symptoms
When setting project preferences for an EPS node in P6 EPPM, users encounter the following:
1. The project preferences (e.g. Calendar and Rate Type fields) initially apply correctly to all projects within the EPS node.
2. When a new project is added to the EPS node, the preferences are not inherited by this new project.
3. The EPS node’s project preferences are reset to default values after the new project is added.