Incorrect Values Displayed When Importing Excel Files into P6 Web Application (Doc ID 3061144.1)

Last updated on NOVEMBER 27, 2024

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 22.12 to 22.12.17.0 [Release 22.12]
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 24.1 to 24.9 [Release 24.1 to 24.9]
Primavera P6 Enterprise Project Portfolio Management - Version 23.12 to 23.12.9.0 [Release 23.12]
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR

When importing an Excel file into the P6 web application, the values in the Remaining Duration column are displayed incorrectly.

EXPECTED BEHAVIOR

When importing an Excel file into the P6 web application, the values in the Remaining Duration column should be displayed accurately.

STEPS TO REPRODUCE:

  1. Open P6 Web.
  2. Generate an Excel template via Projects > Activities > Actions > Import > Create Import Template.
  3. Add some random activities to the generated Excel template.
  4. Go to P6 Web > Actions > Import > Import from Excel and select the created Excel file.
  5. Observe that the REMAINING DURATION values are incorrect when using a 6 x 10 hours calendar.
  6. When the calendar is changed to Corporate - Standard Full Time, the REMAINING DURATION values are displayed correctly.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References