ATP Inquiry Is Not Displaying Constraint Message in the ATP Pegging Details When Request Date Is Equal To The Manufacturing Lead Time
(Doc ID 3065615.1)
Last updated on DECEMBER 31, 2024
Applies to:
Oracle Global Order Promising - Version 12.2.6 and laterInformation in this document applies to any platform.
Symptoms
In Order Management / Scheduling / ATP Inquiry - enter org, item name, request date and then click ATP Details
ATP message returned -"Cannot meet request date or latest acceptable date”
BUT - it is not providing constraint message in the pegging region when the request date = item lead time
-- > It shows 1 day late in Lines region
IF the request date is moved earlier e.g. Lines shows 2 days late and then the pegging shows the - this example is Make item so message is 'Manufacturing Lead Time Constraint Date (dd-mon-yyyy)'
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |