Inaccurate Scalar Reads Created Using Verify Dates
(Doc ID 3073043.1)
Last updated on FEBRUARY 26, 2025
Applies to:
Oracle Utilities Meter Data Management - Version 2.5.0.0.0 to 2.5.0.1.1 [Release 2.5]Oracle Utilities Customer to Meter Base - Version 2.9.0.0.0 to 2.9.0.1.1 [Release 2.9]
Information in this document applies to any platform.
Symptoms
Issue - Creating manual override thru 360 view with start date and consumption supplied results in incorrect measurements
Test case -
Test steps and data -
1. Navigate to 360 Degree View Measuring Component. Measuring Component ID - 0617894xxxxx
2. Using New reading, add measurements to the measuring component from 1/10/2025 to 1/15/2025.
3. In the Scalar – Initial Measurement Overly, put in the start date / time where there are existing initial measurement data. Click Load.
4. User will see initial Measurement Data that falls in between the date parameter
5. Select Function -> Create/Override, Enter the reading
6. Click on verify dates button.
7. Scalar Initial Measurement component saved
Observation and Actual Result -
1.Navigate to the Measuring component. Start date / time and measurement date/time is not correct.
2.All the measurements that come between are not marked as Do Not Use automatically by the system.
Excepted Result -
Start date / time and measurement date/time is correct.
All the measurements that come between are marked as Do Not Use automatically by the system.
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
References |