Symptoms

While updating the install event, getting 'Event Date/Time Cannot Be Earlier Than Previous Event's Date/Time' inconsistently.

This issue is occurring while updating install events using both Manual and smart meter install event Business objects.

Steps
1. Configure Cross Installed Meter Request Type
2. Configure Action Method
3. Flush system
4. Find two compatible meters
5. Main > Device Installation > Crossed Installed Meter Process > Add
6. Select Meter 1 - Device - 10234590xxxx

For meter 1, perform multiple ON and OFFs after the initial install date.
7. Select Meter 2 Device - 07524573xxxx
8. Click Swap Meters

Observation -

Error Details
Event Date/Time (01-20-2017 0:00:00 PST) cannot be earlier than a previous event's date/time (02-04-2019 11:08:52 PST)

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.