Additional Planned Orders Are Created Through Supply Chain For Internal Requisitions
(Doc ID 364577.1)
Last updated on JANUARY 03, 2023
Applies to:
Oracle Advanced Supply Chain Planning - Version 11.5.9 and laterOracle Materials Requirement Planning - Version 11.5.9 and later
Information in this document applies to any platform.
Materials Requirement Planning - Version: 11.5.7 to 11.5.10
FORM:MRPSCPWB.FMB - Supply Chain Planner Workbench
EXECUTABLE:MRCNEW - Memory-based Planner
EXECUTABLE:MSCNEW - Memory-Based Planner
FORM:MSCFNSCW.FMB - Planner Workbench
Symptoms
For couple of items, system created additional(orphan) planned orders without any customer demand.
On further analysis,we found that the demand_id for these planned orders is -1.
We have extra lines for this order.
Review of screen shots seems to show that there are two different ways the order is coming in.
STEPS
Sales order created in C52
-- gets supply from C53
-- C53 get supply from C03
-- C03 uses WIP to produce the item
Cause