Constrained Planning - The Planning Time Fence Functionality Is Not Working In An EDD/ECC Plan
(Doc ID 399888.1)
Last updated on AUGUST 30, 2021
Applies to:
Oracle Advanced Supply Chain Planning - Version 11.5.10.2 and laterInformation in this document applies to any platform.
EXECUTABLE:MSONEW - Memory Based Planner
Symptoms
Planning time fence is not being honored in a Constrained EDD (Enforce Demand Due Dates) or in ECC (Enforce Capacity Constraints) plan
STEPS
Setup the item, plan options and profile options to honor the time fence
-- Planning Time Fence Control - Checked in plan options
-- Item setup with user-defined time fence days and this shows in the plan output
-- Profile settings:
MRP:Create Time fence = Y
MRP:Firm Planned Order Time Fence = Y
MSO: Firm Purchase Orders Within Time Fence = Y
MSO: Firm Requisitions Within Time Fence = Y
MSO: Lead Time Control = VIOLATE_MIN_PROC_TIMES
MSO: Respect EDD Scheduling windows for Lead times = Y
Run the plan and observe the results.
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |