Enterprise Performance Foundation (EPF) Programs Display a 'Warning' and 'Completed' Status While the Multi-Process Sub Requests Are Still Processing Successfully (Doc ID 457132.1)

Last updated on NOVEMBER 12, 2008

Applies to:

Oracle Enterprise Performance Foundation - Version: 11.5.10.2
FEM
This problem can occur on any platform.

Symptoms

While running either the Dimension Member Loader Program or Undo process (Executed Rule Removal or Executed Rule Request Removal), find that the master request appears with a Status = 'Complete' and a red X while the spawend subprocesses are still running.

EXPECTED BEHAVIOR
Expect that the master request in Process Management should not show a status of Complete until
the entire job (including all spawned sub-processes) are also complete.

-- Steps To Reproduce:
The issue can be reproduced at will with the following steps:
1. Submit 'Dimension Member Loader' program
2. View the request before all sub processes have completed (Process Management -> Requests
-> View Requests)
3. View the same request in Concurrent Manager (Forms responsibility)

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms