Symptoms

On 12.0.4 in Test:
Users are testing primary and alternate BOM component scenarios and how the ASCP plan chooses the on hand to peg to both. They are not using substitutes at all. They've seen results where the alternate BOM component is used when pegging on hand before the primary on hand component is exhausted. From internal research this behavior is supposed to be controlled by profile option MSO: Use Existing Supplies in Alternate BOM/Subs. Comp

Summary of customer testing on R12.0.4.  Customer runs Constrained EDD plan with 30 days/7 weeks/3 periods:

A. Profile option MSO: Use Existing Supplies in Alternate BOM/Subs.Comp = 2
The system used the Alternate BOM on hand for the first planned order
The system used the Primary BOM on hand for the second planned order
The system used the Alternate BOM on hand for the third planned order

B. Profile option MSO: Use Existing Supplies in Alternate BOM/Subs.Comp = 0 (which also corresponds to NULL from the notes)
The system used the Primary BOM on hand for the first planned order
The system used the Alternate BOM on hand for the second planned order
The system used the Primary BOM on hand until exhausted on the third planned order


EXPECTED BEHAVIOR
Expect primary BOM on hand to be used up completely first before system uses alternate BOM component on hand

STEPS
The issue can be reproduced at will with the following steps:
1. Create a Primary BOM for a make item with one buy component with on hand
2. Create an Alternate BOM for the same make item in step 1 with one buy alternate component with on hand
3. Create a manual MDS with several entries on the primary end item
4. Run data collections
5. Create an EDD constrained plan and make sure only Use Alternate BOM/Routing is enabled with nothing else in the decision rules.
6. Run the plan with different settings for profile option MSO: Use Existing Supplies in Alternate BOM/Subs.Comp and observe results

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.