'Update From Benchmark' Does Not Copy Project/Subproject (Doc ID 738867.1)

Last updated on OCTOBER 16, 2016

Applies to:

Oracle Utilities Work and Asset Management - Version: 1.7.15.2.2
This problem can occur on any platform.

Symptoms

When you use the action 'Create Work Order from Benchmark', if the Benchmark has a Project/Subproject, it is carried over to the Work Order that is created.
However, the 'Update from Benchmark' action on the Work Order Header does not copy the
Project/Subproject from the Benchmark to the Work Order.

Steps to Reproduce

Pull up an existing Work Order in Planning status
Select the 'Update from Benchmark' action
Enter a Benchmark that has a Project/Subproject
Do NOT select any of the indicators
Hit Finish
While all other information from the Benchmark is updated on the Work Order, the
Project/SubProject is NOT.



Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms