Ascp Plan Is Suggesting Excess Planned Orders. (Doc ID 739561.1)

Last updated on NOVEMBER 15, 2016

Applies to:

Oracle Advanced Supply Chain Planning - Version 11.5.10.2 and later
Information in this document applies to any platform.
*** Checked for relevance on 23-May-2013 ***
*** Checked for relevance on 15-Nov-2016 ***


Symptoms

On 11.5.10.2 :
We are running Enforce Capacity Constraints (ECC) and optimized plan.We are using Fixed Lot Multiplier (FLM) and Minimum Order Quantity (MOQ) for the components.ASCP plan is suggesting planned orders in excess, e.g. Planned Orders are getting generated for the components, even though there is sufficient onhand/purchase order present for that component.

Thus we are not able to release these planned orders and send the schedules to the suppliers as it will lead to excess inventory.



EXPECTED BEHAVIOR
Expect to have planned orders suggested as per the requirements and utilize the existing supply

STEPS
The issue can be reproduced at will with the following steps:
1. Responsibility : Advanced supply chain planning
2. Navigation : Advanced supply chain plannig > Supply chain planning > Workbench > Check for the supply and demand .


Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms