Modify A "Completed" Task In PPM (Doc ID 752103.1)

Last updated on AUGUST 08, 2017

Applies to:

Oracle Agile Product Portfolio Management - Version 9.2.2.0 and later
Oracle Agile PLM Framework - Version 9.2.2.0 and later
Information in this document applies to any platform.
***Checked for relevance on 02-Apr-2012***


Symptoms

Unable to modify a "Completed" Task

Steps To Reproduce:
1. Create a program as new or from a template
2. Set the SmartRule "Enable addition of new task, phases to Completed Activities" = Allow.
3. Create "Criteria" - Task --> General Info.Status = $STATUSTYPE.COMPLETE or
General Info.Status is not null
4. Create Privilege - Modify Completed tasks and add criteria above.
5. Set the program to complete
6. Try to edit the program now


Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a