Symptoms

When profile option MSC: BUY ORDER PROCESSING LEAD TIME CALENDAR = Organization calendar, in calculating PTF, the planning engine was still using 24*7 to offset the full lead time. This is fixed in one of patch 7310622: One off patch for <bug 7237115> on RUP#26.However, this issue is not fixed in higher RUPs.



Steps To Reproduce::
1. ASCP Responsibility
2. Run ASCP Plan

Cause