Scheduled Periodic Appsflow Launches Flow on Wrong Schedule (Doc ID 754333.1)

Last updated on SEPTEMBER 06, 2016

Applies to:

Oracle Preventive Controls Governor - Version 5.1.2 and later
Information in this document applies to any platform.
This problem can occur on any platform.

Symptoms

Problem Statement:
When periodic process flow is scheduled to launch once in a day, it is launched for multiple times instead of once in a day.

Steps to Reproduce:
1. Define Periodic process flow in Appsflow rule form.

2. Select event type as Periodic and define the launch criteria. In launch criteria select schedule type as 'Days' and frequency as '1' and save it.This will launch multiple flows.

Cause