PTD,DD And Other Dates Showing As "Next Day" From Day They Are Due (Doc ID 755795.1)

Last updated on AUGUST 31, 2016

Applies to:

Oracle Communications MetaSolv Solution - Version: 6.0.15 and later   [Release: 6.0.15 and later ]
Information in this document applies to any platform.

Symptoms

When printing or previewing the CLR, the PTD, DD and some other dates appear to be different from the date that is there for these tasks in the task maintenance window. For example, the PTD task on the order has a due date of 10/17/08, but the CLR preview or printout will show it as 10/18/08.

Cause

Sign In with your My Oracle Support account