Plan Shows Overstock Without Suggestion To Reschedule Or Cancel Orders (Doc ID 763460.1)

Last updated on DECEMBER 01, 2015

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.0.4 and later
Information in this document applies to any platform.

Symptoms

A lot of existing supplies
Generating excess stock as there is not enough demand to use them.

Job completes in March 2009 and is pegging to demand as late as Jan 2010

We would expect the job to be canceled or rescheduled out into the future.

STEPS
Run unconstrained plan

Cause

Sign In with your My Oracle Support account