Does ATP Use Profile MSC: Buy Order Processing Lead Time Calendar? ATP Scheduling For Buy Item Based On 24 X 7 Calendar (Doc ID 791135.1)

Last updated on JUNE 28, 2017

Applies to:

Oracle Global Order Promising - Version 11.5.10 to 12.2 [Release 11.5 to 12.2]
Information in this document applies to any platform.
*** Checked for relevance on 15-Sep-2011 ***


Goal

Does ATP honor the new Planning profile MSC: Buy Order Processing Lead Time Calendar?

SCENARIO:
We have set this profile set for Org Manufacturing Calendar so that planning will use our 5 on / 2 off organization calendar to calculate the Processing Lead Time for items.

But when we use ATP results and schedule Sales Orders, ATP is calculating the Processing Lead Time using a 24 x 7 calendar and provides different ATP dates. We need ATP to calculate using the Org calendar.

Solution

Sign In with your My Oracle Support account