Symptoms

On 12.0.4 and above
Find if you create a discrete job with a completion date of a "Monday" date with a time of 00:00:00 (the default) - the system sets the completion date back to Saturday.

EXPECTED BEHAVIOR
Expect the completion date to stay Monday

STEPS
The issue can be reproduced at will with the following steps:
1. Create a discrete job
2. Set the completion date to Monday
3. Time defaults to '00:00:00'
4. System set the completion date back to Saturday

BUSINESS IMPACT
The issue has the following business impact:
Due to this issue, users have to change the time to anything other than '00:00:00'


.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References

My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.