MSCNSP - Memory Based Snapshot Failed in mrllpi_load_planned_items Due To ORA-01455 (Doc ID 815995.1)

Last updated on APRIL 27, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 11.5.9 and later
Information in this document applies to any platform.
EXECUTABLE:MSCNSP - Memory-Based Snapshot

Symptoms

Users are running an ASCP plan.  However the plan fails in MSCNSP - Memory Based Snapshot errors in just a few seconds with the following error:

.Loading workday calendar. Please wait . 0:01
APP-FND-01564: ORACLE error 1455 in mrllpi_load_planned_items

Cause: mrllpi_load_planned_items failed due to ORA-01455: converting column overflows integer datatype

The SQL statement being executed at the time of the error was: select sr_tp_id ,partner_type from msc_trading_partners where ((calen and was executed from the file 7142428/msc/lib/mslsii.pc.
APP-MRP-22075: An internal error has occurred (mrsnii_snp_item_info, 103, , )
APP-MRP-22075: An internal error has occurred (main, 10, 130, DPROD)

Statement with the error:
select sr_tp_id ,partner_type from msc_trading_partners where ((calen
7142428/msc/lib/mslsii.pc


STEPS
--------
Run normal processes for planning:
-- Data Collections
-- Launch Plan
-- Snapshot fails with multiple errors

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms