My Oracle Support Banner

Pipeline Takes More Than Fourteen Hours To Start (Doc ID 864424.1)

Last updated on SEPTEMBER 24, 2016

Applies to:

Oracle Communications Billing and Revenue Management - Version: 7.3.1.0.0 and later   [Release: 7.3.1 and later ]
Information in this document applies to any platform.

Symptoms

The IFW (Pipeline Manager) process is not getting started, even after fourteen hours. Before it took less than four hours to start. The module that takes longer to complete is the DAT::BalanceDataModule.

After analysing the process log, it shows that it as loaded some "3790785 subBalances" as in memory data and with execution time close to 14 hrs.

But when verify the BRM (Billing & Revenue Management) database in bal_grp_% tables
there are hardly few thousands of the records against that table.


Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
  Symptoms
  Cause
  Solution
  References

My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.