Activity Delayed after Leveling Even Though predecessor Activity is Complete (Doc ID 890115.1)

Last updated on JUNE 29, 2016

Applies to:

Primavera P3 Project Planner - Version: 3.1 and later   [Release: 3.0 and later ]
All Platforms

Symptoms

P3 Leveling stretches an activity with an Actual Start even though all predecessors are complete. Activity is delayed after leveling when the predecessor activity is complete Leveling delays an activity even though neither the activity nor its predecessors have resources assigned.

Cause