Percent Complete Fields and Their Calculations in P6 (Doc ID 891102.1)

Last updated on JULY 17, 2020

Applies to:

Primavera Contractor - Version 5.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 5.0 and later
Primavera P6 Professional Project Management - Version 5.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service
All Platforms

Purpose

This document describes the calculations used for each Percent Complete field in P6 Project Management.

Scope

 

Details

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Purpose
Scope
Details
 Activity Percent Complete Fields
 Cost Related Percent Complete Fields
 Unit Related Percent Complete Fields
 WBS Level Percent Complete Field
 Baseline Percent Complete