Work Products and Docs Are Not Linked To Activities When Copying Activities To Different Projects (Doc ID 891511.1)

Last updated on JUNE 29, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version: 5.0 and later   [Release: 5.0 and later ]
Primavera P6 Professional Project Management - Version: 5.0 and later    [Release: 5.0 and later]
All Platforms

Symptoms

When copying an Activity or WBS node from one project to another, the Work Products and Docs do not remain attached to the Activity.


Cause