Goal

P3 has an Import feature to bring data from Microsoft Excel into P3.  The goal of this document is to provide instruction for importing Project data from Microsoft Excel.

The following instructions are specific for Microsoft Excel. However, P3 supports all generic spreadsheet formats.

For Import Troubleshooting Guide, see also <Note 911525.1>.
For more detailed explanation of the import/export process, see also <Note 892128.1>.

Solution