How Is Estimate to Complete (ETC) Calculated in P6? (Doc ID 891746.1)

Last updated on NOVEMBER 21, 2020

Applies to:

Primavera P6 Professional Project Management - Version 5.0 and later
Primavera Contractor - Version 5.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 5.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 8.2.4.0 and later
Primavera P6 Standard Project and Portfolio Management Cloud Service - Version 16.2.13.0 and later
All Platforms

Goal

What does ETC stand for and how is it calculated in P6?

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
Solution
 ETC = PF * (BAC-BCWP) where PF=1
 ETC = PF * (BAC-BCWP) where PF=1/CPI
 ETC = PF * (BAC-BCWP) where PF=1/(CPI*SPI)
 ETC = PF * (BAC-BCWP) where PF=Customized Value