Global calendars changed to 8 hours after running PFXW (Doc ID 891831.1)

Last updated on JUNE 29, 2016

Applies to:

Primavera SureTrak - Version: 3.0 and later   [Release: 3.0 and later ]
All Platforms

Symptoms

After using PFXW on an hourly planned concentric P3 project that contains resource definitions, the global calendar is set to an 8 hour day.

Cause