Budgeted Cost Recalculates To Zero After An Actual Start Is Placed On The Activity (Doc ID 892208.1)

Last updated on JANUARY 30, 2022

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 5.0 and later
Primavera Contractor - Version 5.0 and later
Primavera P6 Professional Project Management - Version 5.0 and later
All Platforms

Symptoms

  • Budgeted Cost recalculates to zero after an Actual Start is placed on the activity
  • Budgeted Cost is deleted when updating Project
  • Budgeted Cost recalculates to zero when Original Duration changes
  • Negative Budgeted Cost resets to zero after Applying Actuals on an activity

Cause

To view full details, sign in with your My Oracle Support account.