Date Constraints and Calendar Dates are Not Holding for Dates Beyond the Current Year (Doc ID 892440.1)

Last updated on JUNE 29, 2016

Applies to:

Primavera P3 Project Planner - Version: 3.1 and later   [Release: 3.0 and later ]
All Platforms
Checked for relevance on 19-Apr-2010

Symptoms

Unable to add a constraint that is not in the current year.  The month and day are correct but the year always reverts back to the current year.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms