Different Data Date Lines In Top And Bottom Views Of The Tracking View And In Portfolio Analysis (Doc ID 892950.1)

Last updated on JUNE 30, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 5.0 and later
Primavera P6 Professional Project Management - Version 5.0 and later
All Platforms

Symptoms

In the Tracking View Portfolio Analysis module, two different data date lines appear when viewing the Gantt Chart and Profile.  The Data Date in the bottom view is correct, but the top view shows a different date.

Cause