Why Are Relationships To Other Projects Ignored When Scheduling? (Doc ID 894143.1)

Last updated on JUNE 30, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 5.0 and later
Primavera P6 Professional Project Management - Version 5.0 and later
All Platforms

Symptoms

External relationships to other projects are being ignored when scheduling. Activities in one project are driven by the relationships to predecessors in another project, however, the activities are scheduled from the Project start rather than the external relationship.

Cause