Cannot Store Period Performance: Actual Start date is Later than the Data Date (Doc ID 895011.1)

Last updated on JUNE 30, 2016

Applies to:

Primavera P3 Project Planner - Version: 3.1 and later   [Release: 3.0 and later ]
All Platforms

Symptoms

Receive the following exception when trying to store period performance:
  • "Actual start date is later than the Data date."
However, the Data date is after the Actual start date of the activity and actual finish is later then the data date.

Cause