Goal

The document explains how to edit the time on an activity's constraint date.

On the activity's Status tab, open the Date window for the constraint.

 >" />

Notice the Hour field is not editable.

This reason the Hour field is not editable is that the option "Do not show time" is chosen in Edit, User Preferences, Dates.

 >" />