My Oracle Support Banner

How To Edit The Time On An Activity's Constraint Date (Doc ID 895613.1)

Last updated on JULY 13, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version: 5.0 and later   [Release: 5.0 and later ]
All Platforms
***Checked for relevance on 21-Sep-2010***

Goal

The document explains how to edit the time on an activity's constraint date.

On the activity's Status tab, open the Date window for the constraint.

 >" />

Notice the Hour field is not editable.

This reason the Hour field is not editable is that the option "Do not show time" is chosen in Edit, User Preferences, Dates.

 >" />

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
  Goal
  Solution

My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.