Symptoms

1. Planned dates do not match Early Dates when Scheduling.
2. The As Late As Possible constraint does not affect Planned Dates (i.e. Planned Start, Planned Finish) or Current Dates (i.e Start, Finish), but only Early Dates (i.e. Early Start, Early Finish).