Activity Original Duration Changes When Calendar Is Changed And One Role Assignment Has Zero Budgeted Units Or Budget Units/Time (Doc ID 896142.1)

Last updated on JUNE 30, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 3.5 and later
Primavera Contractor - Version 4.0 and later
All Platforms
***Checked for relevance on 21-Jun-2011***
***Checked for relevance on 10-May-2013***

Symptoms

Original Duration on the activity changes when activity calendar is changed and at least one Role Assignment has zero Planned/Budgeted Units or Planned/Budget Units/Time

Steps to Duplicate:

1. Create a new activity with the following attributes:

Notice the OD of 40 and a Finish date of 14-Jan-05 17:00.