How To Copy Activity Code Values From One Code To Another And Re-Assign The Value Assignments Accordingly? (Doc ID 896469.1)

Last updated on JUNE 23, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 6.1 and later
Primavera P6 Professional Project Management - Version 6.1 and later
All Platforms

Goal

This document explains how to copy Activity Code Values from one code to another and re-assign the value assignments accordingly.

Solution