How to show the 'Average' usage on the Resource Usage Profile (Doc ID 897757.1)

Last updated on JUNE 29, 2016

Applies to:

Primavera P6 Professional Project Management - Version 6.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 6.0 and later
Primavera Contractor - Version 4.1 and later
All Platforms
***Checked for relevance 22-Feb-2012***
***Checked for relevance 02-Aug-2013***

Goal

To explain how to show the 'Average' usage on the Resource Usage Profile, man-days instead of man-hours, and the number of resource assignments instead of total units. .


Solution