'Recalculate Actual Units And Cost When Duration % Complete Changes' Not Working (Doc ID 898755.1)

Last updated on MAY 23, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 5.0 and later
Primavera P6 Professional Project Management - Version 5.0 and later
Primavera Contractor - Version 5.0 and later
All Platforms
***Checked for relevance on 19-Dec-2012***

Symptoms

Actual Units and Costs are not being recalculated, although the option to 'Recalculate Actual Units and Costs when duration percent complete changes' is checked

Cause