The Planned Value Labor Units Does Not Appear To Spread Correctly In The Activity Usage Spreadsheet (Doc ID 899508.1)

Last updated on JULY 31, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 6.1 and later
All Platforms
***Checked for relevance 11-May-2012***

Symptoms

The Planned Value Labor Units does not appear to spread correctly in the Activity Usage Spreadsheet.


The Planned Value Labor Units is calculated as BL Planned Labor Units * Schedule % Complete.


In this example the Planned Value Labor Units is 16.98 days. When looking at the Planned Value Labor Units spread in the Activity Spreadsheet it's not spreading the 16.98 days.

Cause