An Asterisk (*) Appears In The Dates Column But The Activity Has No Constraints (Doc ID 900009.1)

Last updated on JUNE 30, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 5.0 and later
Primavera Contractor - Version 5.0 and later
All Platforms
***Checked for relevance on 05-Apr-2011***
***Checked for relevance on 17-Jul-2013***

Symptoms

An asterisk (*) appears next to the date in the Start or Finish column when no constraints have been applied to the activity.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms