Sample Global Change To Increase Remaining Duration By A 'Multiplier' User Defined Field (Doc ID 900200.1)

Last updated on JUNE 30, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version: 5.0 and later   [Release: 5.0 and later ]
All Platforms
***Checked for relevance on 19-Nov-2010***

Goal

This document explains how to create a Global Change to multiply the Remaining Duration.

Solution