Is it possible to have the same columns available for Baseline 2 (BL2) and Baseline 3 (BL3) as are available for Baseline 1 (BL1)? (Doc ID 900343.1)

Last updated on JULY 24, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 6.1 and later
All Platforms

Symptoms

Is it possible to have the same columns available for Baseline 2 (BL2) and Baseline 3 (BL3) as are available for Baseline 1 (BL1)?

In the Activities View the columns available for BL1 include:
BL1 Completed Activities
BL1 Duration
BL1 Expense Cost
BL1 Finish
BL1 In-Progress Activites
BL1 Labor Cost
BL1 Labor Units
BL1 Material Cost
BL1 NonLabor Cost
BL1 NonLabor Units
BL1 Non-Started Activities
BL1 Start
BL1 Total Cost

In the Activities View the only columns available for BL2 and BL3 include:
BL2 Finish
BL2 Start
BL3 Finish
BL3 Start

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms