How To Display A Bar That Shows The Difference Between The Baseline Dates And The Current Dates (Doc ID 900413.1)

Last updated on JUNE 30, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 6.2 and later
Primavera P6 Professional Project Management - Version 6.2 and later
All Platforms
***Checked for relevance on 06-Dec-2013***

Goal

This document explains how to display a bar that shows the difference between baseline dates and current dates.

Solution