Changing Resource Rate Does Not Update Baseline Costs (Doc ID 900540.1)

Last updated on JUNE 30, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version: 4.1 and later   [Release: 4.1 and later ]
All Platforms
***Checked for relevance on 14-Feb-2011***

Symptoms

Baseline costs on resource assignments do not update after changing the resource Price/Unit and running Tools, Recalculate Assignments Costs.

Cause