Symptoms

ACTUAL BEHAVIOR

At completion values differ from resource usage spreadsheet to stacked histogram.

For example:

STEPS TO REPRODUCE

  1. Create a New Project
  2. Add an activity and give it 30 days of duration using a 5 day calendar
  3. Add a new resource or role to the role dictionary. Enterprise, Resources or Roles, Click Add.
  4. Add the resource or role to the new activity.
  5. Set Budgeted/Planned Units on the resource or role to 1000hrs
  6. Put an Actual Start on the activity
  7. Schedule the project two months out.
  8. Finish the activity
  9. Show the activity usage spreadsheet on top (View, Show on top, Activity usage spread). Change spreadsheet fields to Time interval, Units, At Complete Labor units.
  10. Show the Resource usage profile on the bottom, and change it to Role if necessary (Display, Select View, By Role). In the Graph area right-click and choose, Resource or Role Usage Profile Options.
  11. Create a filter for that resource or role.
  12. Note - Values for Stacked Histogram do not match At complete Units in the spreadsheet view.

EXPECTED BEHAVIOR

The resource usage spreadsheet at completion values to match the at completion values within the stack histogram.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms