How To Add A Lump Sum Cost To An Activity Without Resources (Doc ID 900819.1)

Last updated on FEBRUARY 14, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 5.0 and later
Primavera Contractor - Version 5.0 and later
All Platforms
***Checked for relevance on 12-Apr-2011***
***Checked for relevance on 28-Sep-2012***


Goal

This document explains how to cost load an activity without resources assignments and how to avoid the error when entering a lump sum cost to activities with no resources: "Cannot set cost because there is no price."

Solution