"Assignment Remain Start Date Cannot Be Earlier Than The Activity Remain Start Date." In P6 After Adding Resource Assignments Through API Or SDK

(Doc ID 900877.1)

Last updated on JUNE 30, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 4.1 and later
Primavera P6 Professional Project Management - Version 4.1 and later
All Platforms
***Checked for relevance on 18-Jun-2012***

Symptoms

 The message "Assignment Remain Start Date cannot be earlier than the activity Remain Start Date" appears in P6 Project Management client after adding resource assignments through API or SDK.

Cause

Sign In with your My Oracle Support account