How to Retain Interproject Relationships When Importing P3 Subprojects as Separate Projects (Doc ID 901205.1)

Last updated on JUNE 30, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version: 4.1 and later   [Release: 4.1 and later ]
Primavera P6 Professional Project Management - Version: 4.1 and later    [Release: 4.1 and later]
All Platforms

Goal

How can relationships between Activities in different Sub-Projects be imported into Project Management from P3 when importing the Sub-Projects as Separate Projects.

Solution