How To Import EPS Activity Code Assignments From An XER File (Doc ID 901318.1)

Last updated on JUNE 30, 2016

Applies to:

Primavera P6 Professional Project Management - Version 5.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 5.0 and later
All Platforms
***Checked for relevance on 15-JULY-2014***

Goal

This document explains how to import EPS level activity code assignments from an XER file.

When importing EPS-level Activity Codes, the Activity Code must already exist in the EPS node you are importing into as well as be assigned to an activity, or any higher EPS nodes in its hierarchical branch.  This includes its parent nodes and the parents of its parent node etc... going all the way up to its respective root EPS node.

Examples:

For all the following examples, please refer to the screenshots below them.

Case 1:  If you import a project with an EPS activity code called Act 1 into EPS level 1, the activity codes will import.  This is because, an activity code called Act 1 exists within that EPS node.

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms