How To Create A Report To Show Resource Usage Based On Early And Late Dates Like P3 Resource Tabular Report (Doc ID 901501.1)

Last updated on JUNE 30, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version: 5.0 and later   [Release: 5.0 and later ]
Primavera P6 Professional Project Management - Version: 5.0 and later    [Release: 5.0 and later]
All Platforms
***Checked for relevance on 30-Nov-2011***

Goal

This document explains how to set up a report to show resource usage based on Early and Late dates, like the Resource Tabular report in P3.

Solution